Supply Projects
Printable Version
This program of tenders has been prepared to reflect Action 3.1 of Tasmania’s Affordable Housing Action Plan 2019-2023 (Action Plan 2). This program represents the capital projects that the Department of Communities Tasmania intends to facilitate through to 2023 to meet the targets established under Action Plan 2.
The program is indicative only and dates may change due to a number of elements. Supply targets are also provided as an indication of the likely scale of each project. Again, these may change depending on a number of factors.
Any significant changes to the program will be published as a revised program on the Communities Tasmania website.
For new social housing projects, the Department has developed a Map of Social Housing Demand to show areas of high demand for social housing in Tasmania.
Capital Project Briefs
During October 2019, young people who reside in supported accommodation facilities were consulted by Housing Tasmania to verify which features of building they preferred and to raise ideas for improving their homes in the future. The purpose of consulting young residents was to inform the design of new supported accommodation facilities to be delivered in Burnie, Hobart, Devonport and Launceston.’
These new projects are described in the program of tenders on this page and are in the pipeline of new assets described in the Affordable Housing Action Plan 2019-23. The findings of the consultation process are outlined in the Consultation Report -
New Youth Supported Accommodation Projects - February 2020.
Project Name | Wirksworth Integrated Aged Care |
---|
Description | Accommodation for elderly Tasmanians |
---|
Region | South |
---|
Tender Type | Construction |
---|
Tender Date | June 2019 |
---|
Target Group | Pre-qualified Building Contractors |
---|
Estimated Number of Units | 50 |
---|
Estimated Value of Construction | $15 million |
---|
Construction Period | July 2020 – April 2022 |
---|
Project Name | Goulburn Street Units, Hobart |
---|
Description | Construction of units for older persons |
---|
Region | South |
---|
Tender Type | Construction |
---|
Tender Date | June 2019 |
---|
Target Group | Pre-qualified Building Contractor |
---|
Estimated Number of Units | 25 |
---|
Estimated Value of Construction | $9 million |
---|
Construction Period | October 2019 - January 2021 |
---|
Project Name | Community Housing Supply Grants |
---|
Description | Construction of new social housing fort priority applicants |
---|
Region | Statewide |
---|
Tender Type | Grants |
---|
Tender Date | July 2019 |
---|
Target Group | Registered community housing providers |
---|
Estimated Number of Units | 147 |
---|
Estimated Value of Construction | $31 million |
---|
Construction Period | January 2020 - December 2022 |
---|
Project Name | Regional Supply |
---|
Description | Construction of units across regional and rural areas |
---|
Region | Statewide |
---|
Tender Type | Grants |
---|
Tender Date | July 2019 |
---|
Target Group | Community Housing Providers and Non-Government Organisations |
---|
Estimated Number of Units | 40 |
---|
Estimated Value of Construction | $8 million |
---|
Construction Period | October 2019 - December 2020 |
---|
Project Name | Channel Highway, Huntingfield |
---|
Description | Initial infrastructure works for 500 lot subdivision |
---|
Region | South |
---|
Tender Type | Construction – civil works |
---|
Tender Date | Mid-2020 |
---|
Target Group | Civil contractors |
---|
Estimated Number of Lots | 470 |
---|
Estimated Value of Works | $4 million |
---|
Construction Period | Late-2021 - Delivery TBA |
---|
Project Name | Regional Supply |
---|
Description | Construction of units across regional and rural areas |
---|
Region | Statewide |
---|
Tender Type | Grants |
---|
Tender Date | July 2020 |
---|
Target Group | Community housing providers and non-government organisations |
---|
Estimated Number of Units | 40 |
---|
Estimated Value of Construction | $8.5 million |
---|
Construction Period | October 2020 – September 2022 |
---|
Project Name | Older Men’s Homeless Accommodation |
---|
Description | Construction of new units to accommodate formerly homeless men |
---|
Region | South |
---|
Tender Type | Construction |
---|
Tender Date | March 2020 |
---|
Target Group | Pre-qualified Building Contractors |
---|
Estimated Number of Units | 7 |
---|
Estimated Value of Construction | $1.5 million |
---|
Construction Period | April 2020 – December 2020 |
---|
Project Name | Homes for Clients with Exceptional Needs |
---|
Description | Units for NDIS clients |
---|
Region | Statewide |
---|
Tender Type | Construction |
---|
Tender Date | June 2020, December 2020, June 2021, March 2022 |
---|
Target Group | Pre-qualified Building Contractors |
---|
Estimated Number of Units | 8 |
---|
Estimated Value of Construction | $2.8 million |
---|
Construction Period | July 2020 – December 2022 |
---|
Project Name | Thyne House Expansion |
---|
Description | Increase the capacity of Thyne House for young people |
---|
Region | North |
---|
Tender Type | Construction |
---|
Tender Date | November 2020 |
---|
Target Group | Pre-qualified Building Contractors |
---|
Estimated Number of Units | 20 |
---|
Estimated Value of Construction | $4.5 million |
---|
Construction Period | March 2021 – February 2022 |
---|
Project Name | Waratah Redevelopment |
---|
Description | Long-term supported accommodation for homeless men |
---|
Region | South |
---|
Tender Type | Construction |
---|
Tender Date | February 2020 |
---|
Target Group | Pre-qualified Building Contractors |
---|
Estimated Number of Units | 24 |
---|
Estimated Value of Construction | $4.3 million |
---|
Construction Period | March 2020 – November 2020 |
---|
Project Name | Oakleigh Court Redevelopment |
---|
Description | Redevelopment of Oakleigh Court into an age-specific complex for older people. |
---|
Region | South |
---|
Tender Type | Construction |
---|
Tender Date | March 2020 |
---|
Target Group | Pre-qualified Building Contractors |
---|
Estimated Number of Units | 50 one-bedroom units |
---|
Estimated Value of Construction | $4.2 million |
---|
Construction Period | July 2020 – December 2021 |
---|
Project Name | Bowick Street, Wynyard |
---|
Description | Subdivision of land |
---|
Region | North-West |
---|
Tender Type | Design and Construct |
---|
Tender Date | February 2021 |
---|
Target Group | Civil contractors |
---|
Estimated Number of Lots | 62 |
---|
Estimated Value of Works | $6.2 million |
---|
Construction Period | May 2021 - Delivery TBA |
---|
Project Name | 39A North Fenton Street, Devonport |
---|
Description | Subdivision of land |
---|
Region | North-west |
---|
Tender Type | Construction – civil works |
---|
Tender Date | March 2021 |
---|
Target Group | Civil Contractors |
---|
Estimated Number of Lots | 10 |
---|
Estimated Value of Works | TBA |
---|
Construction Period | TBA |
---|
Project Name | Burtonia Street, Rokeby |
---|
Description | Subdivision of land |
---|
Region | South |
---|
Tender Type | Construction – civil works (Mission Australia Housing) |
---|
Tender Date | December 2021 |
---|
Target Group | Civil Contractors |
---|
Estimated Number of Lots | 48 |
---|
Estimated Value of Works | $2 million |
---|
Construction Period | Mid-2021 - Delivery TBA |
---|
Project Name | Burnie Youth Foyer |
---|
Description | Facility to provide crisis and medium term housing for under 25’s |
---|
Region | North-West |
---|
Tender Type | Construction |
---|
Tender Date | June 2021 |
---|
Target Group | Pre-qualified Building Contractors |
---|
Estimated Number of Units | 31 |
---|
Estimated Value of Construction | $9.5 million |
---|
Construction Period | October 2021 – March 2023 |
---|
Project Name | Hobart Youth Foyer |
---|
Description | Facility to provide supported housing for under 25’s |
---|
Region | South |
---|
Tender Type | Construction |
---|
Tender Date | September 2021 |
---|
Target Group | Pre-qualified Building Contractors |
---|
Estimated Number of Units | 25 |
---|
Estimated Value of Construction | $9.5 million |
---|
Construction Period | July 2022 – May 2023 |
---|
Project Name | Community Homes for Mental Health |
---|
Description | Groups of units for people with mental illness |
---|
Region | Statewide |
---|
Tender Type | Construction |
---|
Tender Date | March 2021, September 2021 |
---|
Target Group | Pre-qualified Building Contractors |
---|
Estimated Number of Units | 24 |
---|
Estimated Value of Construction | $5.5 million |
---|
Construction Period | April 2021 – September 2022 |
---|
Project Name | Magnolia House Expansion |
---|
Description | Units for women and families |
---|
Region | North |
---|
Tender Type | Construction |
---|
Tender Date | March 2021 |
---|
Target Group | Pre-qualified Building Contractors |
---|
Estimated Number of Units | 15 |
---|
Estimated Value of Construction | $4 million |
---|
Construction Period | July 2021 – December 2022 |
---|
Project Name | Launceston Youth at Risk Centre |
---|
Description | Units for young people |
---|
Region | North |
---|
Tender Type | Construction |
---|
Tender Date | April 2021 |
---|
Target Group | Pre-qualified Building Contractors |
---|
Estimated Number of Units | 8 |
---|
Estimated Value of Construction | $2.2 million |
---|
Construction Period | August 2021 – June 2022 |
---|
Project Name | Bethlehem House Replacement |
---|
Description | New facility to accommodate formerly homeless men |
---|
Region | South |
---|
Tender Type | Construction |
---|
Tender Date | May 2021 |
---|
Target Group | Pre-qualified Building Contractors |
---|
Estimated Number of Units | 50 |
---|
Estimated Value of Construction | $14.5 million |
---|
Construction Period | September 2021 – April 2023 |
---|